Technical characteristics

                                                                           Technical characteristics
                                                                            Apartment house №25
                                                                           

Number of sections and floors:
1 section, 24 floors.

Walls:

Exterior – prefabricated concrete panels 160 mm thick with external insulation system on ventilated facades, in places loggias and balconies - insulated, plastered and painted.
Interior  – prefabricated ferroconcrete panels 160 and 80 mm thick.
Partition walls - artificial plaster panels 80 mm thick

Overlapping:

Prefabricated ferroconcrete panels 160 mm thick

Loft:

cold.

Roofing:

roll coating.

Rainwater drainage:

interior

Characteristics of fire prevention measures:

Stairs illumination – daylight, night time - electric;
Antismoke protection – according to the project;
Installed fire extinction pipes on every floor and in bathrooms in the apartments(FEP)
Fire extinction automatic system.

Number of elevators:

2 elevators 400kg capacity ;
1 elevator 1000 kg capacity (also for firemen transportation).

Floor height:

2,80 m (floor to floor).

Additional interior works:

Entrance door to the apartment –  metal,shockproof;
Interior doors in the apartment – wooden frame MDF lined;
Windows and balcony doors – plastic with double glazing;
Glazing of balconies and loggias – plastic with single glazing.

Interior finishing works in the apartments:

Rooms, Kitchen, living rooms , halls and hallways:

floor – oilcloth;
walls –  wallpaper;
ceiling –  paste whitewash.

Bathrooms (bathroom, toilet):

floor – hydro isolation and ceramic tiling;
walls and ceiling – finishing interior works not made.

Bathroom equipment :

1-room apartments  - 1 steel bath,  1 wash basin, 1 toilet;

2-room apartments  - 1 steel bath, 2 wash basins, 1 toilet;

3-room apartments  - 1 steel bath, 2 wash basins, 2 toilet;

wash sinks in the kitchen are not installed;

stop bathroom armature and ball valves are installed.

Towel dryers:

electric, not installed. In the bathrooms and joined bathrooms an electric socket for the dryer is installed.

Type of oven:

electric, not installed.

Wiring:

made of copper wires with installation of sockets and switches. The socket for an electric stove is not installed.

Network TV:

Wires (connection) performed to the boards on each floor at the corridor of common use. Connection to the apartment and interior layout not made.

Heating system:

From heat-generating installation on the roof. Two- piped dual-zoned wiring:

first zone – 1 – 12 floors,
second zone – 12 – 24 floors.The wires of heating system made to every apartment of polyethylene pipes in the floor structures.

Type of heating device:

steel radiators

Ventilation system:

Mandatory, in the kitchen and in bathrooms wall ventilators are installed. Each appartament on the facade of the building will have a place prepared for the installation of the outer block of air conditioner (bracket, screen and hole). The air conditioner is not installed.

Cold water supply:

Two-zoned.

First zone – 1 – 12 floors inclusively (water supply - ascendant
Second zone – 24 – 13 floors, inclusively (water supply  - descendant).

Supply pipes are laid in the attic.

Hot water supply:

From heat-generating installation on the roof. Two- piped dual-zoned wiring:

First zone – 12 – 1 floors inclusively (water supply - descendant). First  zone pipelines laid under the ceiling of corridors of common use on the 12 th floor.;
Second zone – 24 – 13 floors inclusively (water supply - descendant). Supply pipes are laid in the attic.
Circular pipelines of second zone are located under the ceiling of corridors of common use on the 12 th floor.
Each apartment dilution of hot and cold water from pipes, placed in corridors of common use, bathrooms and kitchens to the apartments is done with polyethylene  pipes in floor structures.

Counters for each apartment:

electricity;
cold and hot water;
heating.
Located in the corridors of common use blocks.

Finishing works on the corridors of common use:
Elevator hall, corridors of common use and stairs:

stairs floor –  concrete finish;
corridor of common use and elevator hall floor –  ceramic tiling;
elevator hall walls on the 1st floor –  ceramic tiling;
corridor of common use  and elevator hall walls at the typical floors – water resistant paint;
ceiling – paste whitewash;
entrance doors to the building – aluminum glazed;
interior doors –wooden;
windows – metal glazing.


Embellishment:

exterior lighting – according to the project;
roads, pavements, pedestrian paths – asphalt coating and FEM coating;
recreation areas: active rest, playground, temporary parking for vehicles.

                                                                       Attention to the investors!

1. It is forbidden to dismantle independently the constructive elements of the object, interior and exterior works and change the engineering communications.

2. During the construction process the developer has the right to add/ change elements in the design and technological solutions of the residential building that do not degrade its consumer qualities and do not lead to violation of sanitary norms.

3. The total area of the apartment is approximate; final calculations should be made according to the official data of technical inventory.