Technical characteristics


                                                                            Apartment house №22
                                                                            2-24 floors Apartments


Number of sections and floors:
1 section, 26 floors and socle,

– a socle and 1st floor –office areas ;
– 2-24 floors – one-level apartment ;
– 25-26 floors - two-level apartments.


Structure scheme: monolithic ferroconcrete frame.


Walls:
exterior – ceramic brick 250 mm thick, and monolithic ferroconcrete thick 250 mm, plastered in the apartment and monolithic ferroconcrete, with external insulation system over the external system of ventilated facades, in loggias and balconies – external insulation system and with decorative plaster finish;

interior between apartments – ferroconcrete 250 and 300 mm thick; made of small size materials 250 and 300 mm thick, not plastered.

Partition walls: made of small size materials 100 and 120 mm thick, not plastered.

Floor height:  3,00 m (floor to floor).

Overlapping: monolithic ferroconcrete 200mm thick. In the apartments the overlapping is made out of the structure of 80 mm thick, except the WC. At the WC of the apartments a waterproof isolation is made.

Roof: flat, roll coating.

Rainwater drainage: interior.

Characteristics of fire prevention measures:

Lighting of stairs - daylight, at night time –  electric;
Antismoke protection – according to the project;
Installed fire extinction pipes on every floor;
Installed fire extinction pipes in bathrooms in the apartments (FEP).

Garbage chute (location):

garbage receiver – on each floor (except 1st floor) ;
collecting bin – on the 1st (ground) floor.

Number of elevators– 3:

2 elevators 400kg capacity ;
1 elevator 1000 kg capacity (also for firemen transportation).

Additional interior works:

Entrance door to the apartment –  metal,shockproof;
Interior doors - not established;
Windows and balcony doors – plastic with double glazing;
Glazing of balconies and loggias – plastic with single glazing.

Interior finishing works in the apartments: not made.

Bathroom equipment :not made.

Towel dryers: electric, not installed. In the bathrooms and joined bathrooms an electric socket for the dryer is installed.


Type of oven: electric, not installed.

Wiring: made of copper wires with installation of sockets and switches

Network TV: Wires (connection) performed to the boards on each floor at the corridor of common use. Connection to the apartment and interior layout not made.

Heating system: Two- piped dual-zoned wiring, with low dilusion:

first zone
– 1 – 13 floors,
second zone – 14 – 26 floors.The wires of heating system made to every apartment of polyethylene pipes in the floor structures.

Type of heating device: steel radiators

Ventilation system: mandatory, in the kitchen and in bathrooms wall ventilators are installed. Each appartament on the facade of the building will have a place prepared for the installation of the outer block of air conditioner (bracket, screen and hole). The air conditioner is not installed.

Cold water supply: Two-zoned.

First zone – 1 – 13 floors inclusively (water supply - ascendant
Second zone – 25 – 14 floors, inclusively (water supply  - descendant).

Second zone pipelines laid under the ceiling of corridors of common use on the 25th floor.

Hot water supply: Dual- zoned :

First zone – 13 – 1 floors inclusively (water supply - descendant). First  zone pipelines laid under the ceiling of corridors of common use on the 13 th floor.;
Second zone – 25 – 14 floors inclusively (water supply - descendant). The pipelines laid under the ceiling of corridors of common use on the 25 th floor.
Circular pipelines of second zone are located under the ceiling of corridors of common use on the 13 th floor.
Each apartment dilution of hot and cold water from pipes, placed in corridors of common use, bathrooms and kitchens to the apartments is done with polyethylene  pipes in floor structures.

Counters for each apartment:

cold and hot water;
electricity;
heating.
Located in the corridors of common use blocks.

Finishing works on the corridors of common use:
Elevator hall, corridors of common use and stairs:

stairs floor –  concrete finish;
corridor of common use and elevator hall floor –  ceramic tiling;
elevator hall walls on the 1st floor –  ceramic tiling;
corridor of common use  and elevator hall walls at the typical floors – water resistant paint;
ceiling – paste whitewash;
entrance doors to the building – aluminum glazed;
interior doors –wooden;
windows – metal glazing.

Embellishment:

exterior lighting – according to the project;
roads, pavements, pedestrian paths – asphalt coating and FEM coating;
recreation areas: active rest, playground, temporary parking for vehicles.

                                                                       Attention to the investors!

1. It is forbidden to dismantle independently the constructive elements of the object, interior and exterior works and change the engineering communications.

2. During the construction process the developer has the right to add/ change elements in the design and technological solutions of the residential building that do not degrade its consumer qualities and do not lead to violation of sanitary norms.

3. The total area of the apartment is approximate; final calculations should be made according to the official data of technical inventory.